Crawford Creek Tributary

Culvert Under Access Road
Completed in 2000

Issue:

The two culverts under the access road are downstream from where the earthen bridge had collapsed. During the substantial seasonal flows the culverts would become clogged and force water over the dirt roadway delivering additional sediment into the system. Once the blockage is removed, water will flow with greater velocity and projection as nature had intended

Plan:

Remove all the black berry vines, limbs, and sediment from culverts. Place rock diversions along the head of the culverts and bank edges, while maintaining the flow through the culverts and improving sedimentation delivery problems.

Blocked culverts - March 2000

Blocked culverts - March 2000

Heernett Environmental Foundation Crawford Creek Tributary Project

Cleaned culverts - October 2000

Cleaned culverts - October 2000

Heernett Environmental Foundation Crawford Creek Tributary Project

Crawford Creek under medium flow facing West - February 2001

Crawford Creek under medium flow facing West - February 2001
after clean out

Heernett Environmental Foundation Crawford Creek Tributary Project

Crawford Creek under medium flow facing upstream - February 2001

Crawford Creek under medium flow facing upstream - February 2001
after clean out

Heernett Environmental Foundation Projects - created to protect America's Natural Heritage


Heernett Environmental Foundation Logo

Heernett Environmental Foundation

Heernett Environmental Foundation

Heernett Environmental Foundation
Finances | Links | Site Map